Work Order Completed Early
If a work order gets completed before all operations are completed in it's Manufacturing Routing, this may be related to it's Parts Routing.
We have found issues with Tascus versions (prior to 23.9) that will Complete the work order after the 1st operation is complete. This can occur if the Manufacturing Routing for the top-level part number is empty.
See this example below:
In this example, top level Part Number = G093L, with a Parts Routing of G093L_A:

The Manufacturing Routing for G093L is empty:

Only G093L_A has a valid routing:

In Tascus versions 23.8.2 and earlier, this work order will get automatically completed after the 1st operation has finished. In later versions of Tascus, this issue has been resolved.
So for earlier versions, our suggested fix is to copy the Manufacturing Routing to the Top Level part number.
Work Order with Qty > 1 Complete
I have a Work Order with multple items in it, I have completed 1 x item, but it says the entire order has been completed?
This article will help you to configure the Settings to have multiple serial numbers for a Work Order, or to have a single batch number for an entire order.


An explanation below about each option in the drop-down menu: